Issue No. 2 23 May 2003 This is the second in a series of Newsletters which we will publish every 4-6 weeks to our "The Lofts Sathorn" home owners and prospective clients. Our aim is to keep you fully informed on the progress of the development at Soi Meksawat during the period of construction and before transfer. The topics we will keep you updated about will include construction progress, choice of suppliers and materials, programme, meetings, on-site visits, progress of show homes etc. We hope you will find this informative and we welcome any comments from you by telephone, email, fax or ordinary letter. Our contact details are at the bottom of this page. In this Newsletter we will also post photographs taken of the site. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
CONSTRUCTION |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Construction progress is moving along well with bore piling for the sub structure set to be completed by May 23. Bore piles on the
three Lofts at the front of the site (which face Soi Meksawat) have been capped and work is now in progress on the ground beams.
The photographs show how the work has developed since our first Newsletter on April 09 2003. |
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
DESIGN We have decided to fit out one show Loft (Loft 12) rather than two, as Loft 11 has recently been sold. The home will have a contemporary and eclectic Asian feel. Our design team will complete the interior design plan this week and will then go to tender in order that we are able to start interior fit out of the show Loft during the second half of June and complete this work by end July. The show Loft will then be ready for owners and prospective buyers to experience at first hand. The images below will give you an idea of the look and feel we are creating in the living space at the show Loft. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
SITE VISITS The completion and opening of the Show Loft at end July will coincide with a number of marketing events at the site, the details of which we will outline in the next Newsletter Issue No. 3. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
OTHER MATTERS Please look out for the Nation newspaper Property Supplement to be published on Thursday May 29th. This will include an interview with the MD of Raimon Land, Mr Nigel Cornick, and Arthur Napolitano, the MD of Kudu. The supplement will cover, amongst other topics, The Lofts Sathorn. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Please click on a link below for previous Newsletters: Issue No. 1 - 9 April 2003 Issue No. 2 - 23 May 2003 Issue No. 3 - 25 June 2003 Issue No. 4 - 8 August 2003 Issue No. 5 - 1 November 2003 Issue No. 6 - 1 March 2004 Issue No. 7 - 3 June 2004 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||